 |
Summer, 2001
This is the existing boys washroom. Do you think we need
new washrooms?
|
 |
November 8, 2001
Last Friday the footings were poured and today the walls
are being poured. It has rained both days. This view looks South East
toward
the lodge.
|
 |
November 8, 2001
Cement is poured into a styrofoam mold which also serves
as insulation. This view looks North East toward the pond.
|
 |
November 13, 2001
Sand is being brought in from our sand pit and compacted
to prepare for the granular "A" material.
|
 |
November 13, 2001
The granular "A" material is being dumped into
the foundation to be compacted.
|
 |
November 16, 2001
The first wall is erected.
|
 |
November 16, 2001
More walls are erected.
|
 |
November 21, 2001
The walls and overhangs are almost ready for roof trusses.
|
 |
November 22, 2001
The new washrooms are being heated through radiant floor
heating. This shed is being built to store the wood furnace and a large
supply of wood.
|
 |
November 22, 2001
The furnace heats the water and then the water is pumped
through special tubing in the floor to provide a nice, even heat. The
furnace will also supply the hot water for the building.
|
 |
November 26, 2001
The crane arrived at 6:30 a.m. to install the trusses
and left shortly before 11:00 a.m.
It rained all the previous night but stopped during the day.
|
 |
November 26, 2001
This is a view from the pulley ride at the pond. Here
the crane is putting on the final trusses.
|
 |
December 3, 2001
It has been raining lots during this past week, which
has hindered our progress. Here Ken, Steve and Andrew are putting the
strapping on the roof. This picture offers a view of the south entry way
which features a large overhang.
|
 |
December 6, 2001
The rain has finally stopped. Here Steve and Ken are putting
the steel on the roof on the north side.
|
 |
December 12, 2001
For the past three days the crew to drill a new well has
been hard at work. Today they struck water at a depth of 220'. The well
is providing a strong 8 gallon per minute flow of fresh, clean water.
Indeed this is a blessing!
|
 |
February 6, 2002
We are now working on the inside of the washrooms. The
building is now being heated by our outdoor wood furnace which allows
us to work in the ground in the middle of the winter. All the drainage
pipes have been laid.
|
 |
February 13, 2002
The drain pipes have now been covered with sand and a
layer of Styrofoam and wire mesh. Here Steve and Andrew are laying the
radiant floor pipe and tying it to the wire mesh.
|
 |
March 1, 2002
Over the past couple of weeks we have scheduled the concrete
floor to be poured three times but it had to be canceled because of poor
weather. Two days it was too warm and one day it was too cold. Finally,
today, the weather was just right.
|
 |
March 1, 2002
The concrete had to be transported from the truck by wheel
barrel. Thirty cubit yards of concrete were poured to form the floor.
|
 |
March 1, 2002
The concrete is now smoothed out through a screeding process.
One of the manifolds can been seen in the middle of this picture. They
control the flow of water throughout the building.
|
 |
March 15, 2002
Now it is time to focus on the inside walls. This is a
picture taken from the southwest corner (in the laundry room) looking
east.
|
 |
March 15, 2002
This picture is taken from the southeast corner (in the
utility room) looking west. The manifolds for the radiant heat flooring
can be seen in the foreground. The drains for the seven new girl's showers
can be seen behind the manifolds.
|
 |
April 5, 2002
Over the past few weeks the plumbing and electrical has
been roughed in. Here is a picture of Steve working in the girl's washroom
where the sinks will be.
|
 |
April 17, 2002
Things are progressing well these days. Here Andrew is
finishing installing the seven showers in the girls' washroom. Separate
change areas will be built in front of each shower unit.
|
 |
April 25, 2002
The installing of drywall boards was completed today.
This is a view of the hallway outside the boys' washroom entrance.
|
 |
May 3, 2002
Steve is working on the electrical box.
|
 |
May 3, 2002
The drywalling is now complete. Here Andrew is starting
the process of painting. This is the hall entrance into the girls' washroom.
|
 |
May 13, 2002
Two large tile beds are currently being excavated to service
the washrooms. This one is located on the east side between the lodge
and the pond.
|
 |
May 13, 2002
A light green ceramic tile is now being laid on the floor
and a textured white tile on the walls. This view is in front of the boys'
showers. Eventually seven tons of ceramic tile will be laid in the washrooms.
|
 |
May 27, 2002
The ceramic tile continues to be laid. The floor has been
completed and now they are working on the walls. This is a view of the
girls' shower room.
|
 |
May 30, 2002
The new washrooms require two large tile beds. This one
is between the lodge and the pond. There will be over 1500 linear feet
of pipe laid in the ground.
|
 |
June 6, 2002
The ceramic tile is now completed and the lights are in
the process of being installed. This is a view of the entrance to the
girls' washroom.
|
 |
June 6, 2002
This is a view of the east tile bed between the lodge
and the pond. We are working hard to have the washrooms ready to be used
by the summer time.
|
 |
June 13, 2002
We are working hard to have the washrooms ready for the
first session of summer camp. Here Steve and Ken are installing the partitions
in the boys' washroom.
|
 |
June 20, 2002
Everyone is working hard to finish the washrooms before
summer camp begins. The stainless steel sinks and counters are now in.
|
 |
June 30, 2002
The new washrooms are officially usable!! Much has been
done in the past few days including finishing the partitions, installing
hardware and mirrors, finishing the septic system and lots of cleaning.
We are thankful to God for this blessing!
|